Hillmorton Lane Affordable Housing – Monthly reports
Monthly update reports from the developer, Whiterock Homes:
Update on development – 8th September 2023
9 x New Build Development
Land adjacent to Strawfield House, Hillmorton Lane, Yelvertoft
Previous and Planned Works
Completed works:
- Plot 7 roof and solar panels on
- Plot 7 internals started
- Plot 8 trusses on
- Plot 8 garaged roofed in
- Plot 6 brickwork started
- Drainage completed along whole road
- Road being stoned up
- Services (water and electricity) completed for plots 6-9.
Next 4 weeks work include:
- Plot 8 trusses on and tile roof
- Plot 8 and garage internals
- Plot 6 brickwork taken up
- Plot 7 to be plastered
Road works to continue
Update on development – 23rd July 2023
9 x New Build Development
Land adjacent to Strawfield House, Hillmorton Lane, Yelvertoft
Previous and Planned Works
Completed works:
- Brick delivery week commencing Monday 3rd July 2023
- 1st lift scaffolding on plots 7 & 8
- Continue taking up plots 7 & 8
- BT works outside the entrance to the site
- Complete foul drainage dig
- Dig foundations and concrete plots 6 & 9
Next 4 weeks work include:
- Continue taking plot 8 up to second scaffold lift
- Continue taking plot 7 up to roof level and gable scaffold lift
- Commence work on foundational brickwork on plots 7 & 9
- Sort drainage and services out for plots 6 & 9
- Delivery of floor beams for plots 6 & 9
- Floors to go on for plots 6 & 9
- Electric connections
- Commence roadworks
Update on development – 16th June 2023
9 x New Build Development
Land adjacent to Strawfield House, Hillmorton Lane, Yelvertoft
Previous and Planned Works
Completed works:
- Building stone delivery
- 1st load Brick delivery
- Ground works continue
- Complete storm drainage works
- Carry on with road works
- Take up plots 7 & 8
Next
9 x New Build Development
Land adjacent to Strawfield House, Hillmorton Lane, Yelvertoft
Previous and Planned Works
Completed works:
- Building stone delivery
- 1st load Brick delivery
- Ground works continue
- Complete storm drainage works
- Carry on with road works
- Take up plots 7 & 8
Next 4 weeks work include:
- Brick delivery week commencing Monday 3rd July 2023
- 1st lift scaffolding on plots 7 & 8
- Continue taking up plots 7 & 8
- BT works outside the entrance to the site
- Complete foul drainage dig
- Dig foundations and concrete plots 6 & 9
4 weeks work include:
- Brick delivery week commencing Monday 3rd July 2023
- 1st lift scaffolding on plots 7 & 8
- Continue taking up plots 7 & 8
- BT works outside the entrance to the site
- Complete foul drainage dig
- Dig foundations and concrete plots 6 & 9