Hillmorton Lane Affordable Housing – Monthly reports

Monthly update reports from the developer, Whiterock Homes:

Update on development – 8th September 2023

9 x New Build Development

Land adjacent to Strawfield House, Hillmorton Lane, Yelvertoft

Previous and Planned Works

Completed works:

  • Plot 7 roof and solar panels on
  • Plot 7 internals started
  • Plot 8 trusses on
  • Plot 8 garaged roofed in
  • Plot 6 brickwork started
  • Drainage completed along whole road
  • Road being stoned up
  • Services (water and electricity) completed for plots 6-9.

Next 4 weeks work include:

  • Plot 8 trusses on and tile roof
  • Plot 8 and garage internals
  • Plot 6 brickwork taken up
  • Plot 7 to be plastered

Road works to continue

Update on development – 23rd July 2023

9 x New Build Development

Land adjacent to Strawfield House, Hillmorton Lane, Yelvertoft

Previous and Planned Works

Completed works:

  • Brick delivery week commencing Monday 3rd July 2023
  • 1st lift scaffolding on plots 7 & 8
  • Continue taking up plots 7 & 8
  • BT works outside the entrance to the site
  • Complete foul drainage dig
  • Dig foundations and concrete plots 6 & 9

Next 4 weeks work include:

  • Continue taking plot 8 up to second scaffold lift
  • Continue taking plot 7 up to roof level and gable scaffold lift
  • Commence work on foundational brickwork on plots 7 & 9
  • Sort drainage and services out for plots 6 & 9
  • Delivery of floor beams for plots 6 & 9
  • Floors to go on for plots 6 & 9
  • Electric connections
  • Commence roadworks

Update on development – 16th June 2023

9 x New Build Development

Land adjacent to Strawfield House, Hillmorton Lane, Yelvertoft

Previous and Planned Works

Completed works:

  • Building stone delivery
  • 1st load Brick delivery
  • Ground works continue
  • Complete storm drainage works
  • Carry on with road works
  • Take up plots 7 & 8

Next

9 x New Build Development

Land adjacent to Strawfield House, Hillmorton Lane, Yelvertoft

Previous and Planned Works

Completed works:

  • Building stone delivery
  • 1st load Brick delivery
  • Ground works continue
  • Complete storm drainage works
  • Carry on with road works
  • Take up plots 7 & 8

Next 4 weeks work include:

  • Brick delivery week commencing Monday 3rd July 2023
  • 1st lift scaffolding on plots 7 & 8
  • Continue taking up plots 7 & 8
  • BT works outside the entrance to the site
  • Complete foul drainage dig
  • Dig foundations and concrete plots 6 & 9

4 weeks work include:

  • Brick delivery week commencing Monday 3rd July 2023
  • 1st lift scaffolding on plots 7 & 8
  • Continue taking up plots 7 & 8
  • BT works outside the entrance to the site
  • Complete foul drainage dig
  • Dig foundations and concrete plots 6 & 9